DERUI ELECTRIC · SWITCHGEAR PROCUREMENT
12 kV SF₆-Free Switchgear Quotation Checklist: What’s Included?
Public price references, supply scope and the details behind a complete purchasing budget.
With 25 years of power distribution equipment manufacturing experience, DERUI Electric brings a manufacturer's perspective to budgeting for SF₆-free gas-insulated switchgear. A useful quotation connects the price to the equipment and functions your project will receive.
12 kV SF6-Free Switchgear Price: What Do Public Listings Show?
Public supplier listings offer an initial indication of the amounts buyers may encounter when researching a 12 kV SF6-free switchgear price. The examples below were reviewed on September 23, 2026. They are advertised prices, including sample prices, rather than verified transaction prices or DERUI quotations.
| Public supplier listing | Displayed price (USD) | How to interpret it |
|---|---|---|
| Guangdong Zhengchao: ZCKQG-12 dry-air SF6-free switchgear, 12 kV, 630 A | US$4,800 / Piece | Displayed sample price; the included protection, controls and accessories require confirmation. Source 1 |
| Beijing HCRT: listing titled 12 kV dry-air insulated ring main unit | US$7,000 / Piece | Displayed sample price; the page lists multiple ratings and customizable compartments, without tying every option to this price. Source 2 |
| Seven Stars: 11/12 kV dry-air or nitrogen-insulated switchgear | US$1,500–10,000 / Piece | Advertised range; its endpoints are not mapped to a complete circuit configuration and supply list. Source 3 |
These examples provide a price scale, not a like-for-like market average. The US$1,500–10,000 range belongs to one supplier listing; it is not a universal price range for a complete panel or lineup. “Piece” alone does not establish the number of functional units supplied. Freight is subject to supplier confirmation, and tax, installation and commissioning treatment must also be checked.
For an initial SF6-free switchgear budget, connect each amount to a defined configuration and delivery basis. Confirm whether the price covers a single functional unit or a multi-circuit assembly, which functions and accessories are included, and whether it applies to a sample or the planned order quantity. The following checklist helps turn that headline price into a usable purchasing budget.

A 12 kV SF₆-free switchgear budget should account for the complete lineup, operating and protection functions, remote-control requirements, accessories and delivery scope. It should also identify the quotation's validity and any conditions for repricing. A panel price becomes a meaningful basis for comparison when these details are clear.
Our previous article explains why switchgear prices differ even at the same voltage and current ratings. Here, the focus is how to turn a quotation into a more complete purchasing budget.
Does a Single-Panel Price Cover the Complete Switchgear Lineup?
A single-panel price covers the specified unit and its stated scope; it does not automatically cover the complete lineup. Confirm the function and quantity of each unit before calculating the equipment total.
For example, multiplying the price of a load-switch unit by the total number of panels will not establish a reliable budget if the lineup also requires circuit-breaker or metering units. Each serves a different function and carries a different component list.
Ask for an itemized quotation that identifies each functional unit, its configuration, quantity and price. Then check the shared items: busbar connections between modules where applicable, end arrangements, and any enclosure required for the installation.
Clarify accessories separately. Cable connectors, surge arresters and spare parts should each have an explicit supply status. An item missing from the quotation is unresolved scope, not a confirmed saving.
Are Motorized Operation and Protection Relays Extra-Cost Options?
That depends on the functional unit and the configuration already included in the quotation. Review the baseline before adding an allowance for motorization or protection.
The published DERUI HBG-12 product specifications illustrate this distinction:
| HBG-12 unit | Published configuration | Budget question |
|---|---|---|
| C load-switch unit | Manual operation of the vacuum load switch; motorized operation is optional | Does this circuit require motorization, and is it included in the quoted price? |
| V circuit-breaker unit | Vacuum circuit breaker with an electric operating mechanism, protection current transformers and a digital protection relay | Do the quoted relay, protection functions and control power requirements match the project specification? |
These product specifications provide a starting point; the agreed quotation defines the order's supply scope. If a project requires a particular relay model, additional protection functions or metering, identify the difference from the quoted configuration and request a separate price where applicable.
Keep required protection explicit. Optional enhancements and required protection functions should be clearly distinguished when reviewing the budget.
Does Motorized Operation Include Remote Control?
Motorized operation alone does not establish a complete remote-control system. It provides an operating capability that must be connected to the required control arrangement.
Depending on the project, remote operation may also require a remote terminal unit (RTU) or controller, auxiliary power, communication interfaces, status signals, additional wiring and integration work. Some of these may already exist on site or be supplied by another contractor.
State which circuits need remote operation, what commands and signals are required, and which party provides the controller, power supply and communications. If connection to a supervisory control and data acquisition (SCADA) system is required, identify the interface requirements and responsibility for integration and commissioning.
For a project where only selected circuits need remote control, request the relevant additions against those circuits. This makes the cost of each function visible and helps prevent both missing scope and duplicate purchasing.

How Do Copper Prices Affect Switchgear Quotations and Their Validity?
Copper price movements can affect material cost, but do not translate directly into an equal percentage change in the finished switchgear price. The effect depends on the design's copper content, procurement timing and the rest of the equipment's cost structure.
For a purchasing decision, the actionable questions concern the quotation itself: when does it expire, which configuration and quantity does it cover, and what changes would require the supplier to recalculate it?
Record the drawing or specification revision, quantity, currency and delivery basis alongside the quoted price. Ask when the price becomes fixed for the agreed order and what conditions must be met. If the specification, quantity or delivery plan changes before acceptance, request confirmation that the original price still applies.
An expired quotation needs reconfirmation; expiry alone does not establish that the price must rise. Similarly, a material-price movement should not be treated as an automatic change to an agreed order price. The applicable terms need to be clear to both parties.
Switchgear Quotation Checklist: What to Confirm Before Ordering
Assign each item to one of three categories: included in the supplier's price, quoted separately, or provided by the buyer or another contractor. Keep any undecided item visible until its scope and responsibility are agreed.
Costs handled outside the switchgear supplier's scope, such as installation or import charges, should also be accounted for in the project budget.
| Budget item | What to confirm |
|---|---|
| Complete lineup | Functional-unit types, quantities, ratings and applicable connections between units |
| Operation and protection | Operating mechanisms, relay models and functions, current transformers and control power |
| Metering and remote control | Metering requirements, controller or RTU, communication interfaces, signals and integration responsibility |
| Accessories and enclosure | Cable connectors, surge arresters, spares and any required outdoor enclosure |
| Testing and documentation | Included tests and reports, drawings, manuals and any agreed witnessed factory acceptance testing (FAT) |
| Packing and logistics | Packing method, delivery destination, transport, insurance and applicable import charges |
| Site work | Installation and commissioning scope, including work provided by other parties |
| Commercial conditions | Quotation validity, currency, payment terms, delivery schedule and conditions for price confirmation or revision |
Compare suppliers against the same checklist. Where one quotation includes an item and another excludes it, establish the missing cost before deciding which offer fits the budget.
Frequently Asked Questions
Can I request a budgetary quotation before the technical specification is complete?
Yes. Send the available circuit list or preliminary single-line diagram, electrical ratings and estimated quantity. Identify undecided items and ask for assumptions and optional configurations to be stated separately. This estimate can support early budgeting; confirm the final configuration, supply scope and commercial terms before placing an order.
Should I mention future remote-control requirements in the initial enquiry?
Yes. Identify the circuits and functions you expect to add so the supplier can assess the operating mechanisms, control power, interfaces and installation space needed. Ask which provisions are included now and what would need to be added later. Upgrade feasibility and cost depend on the specific design.
Can the same price apply to phased purchases or deliveries?
Do not assume it will. State the planned total quantity, batch quantities and schedule, and clarify whether these form one confirmed order or separate future orders. Ask the supplier to specify the quantity and period covered by the price, the conditions for confirming that price, and whether phased delivery adds packing or logistics charges.
Request an Itemized HBG-12 Switchgear Quotation
Request a DERUI HBG-12 quotation that identifies the required units, included functions and supply scope. Send your single-line diagram or circuit list, electrical ratings, quantity, installation conditions, delivery destination and required schedule. Include any mandatory protection, metering or remote-control requirements.