PD Testing During FAT: What Transformer and Switchgear Buyers Should Check
Product News

PD Testing During FAT: What Transformer and Switchgear Buyers Should Check

2026-11-04

A low partial discharge reading means little without the test conditions behind it. Before accepting a transformer or medium-voltage switchgear panel, buyers should confirm what was tested, how it was measured and which acceptance criteria were applied.

DERUI ELECTRIC manufactures both distribution transformers and medium-voltage switchgear. For projects purchasing these products together, one procurement checklist can help organize the documentation—but the technical requirements must remain specific to each type of equipment.

PD testing during FAT: the essential check
When partial discharge testing forms part of factory acceptance testing (FAT), review the equipment identity, acceptance criteria, test conditions, measurement validity and recorded results. A “Pass” statement or a low pC value alone is not sufficient evidence.

2026年7月31日 09_51_21.png

What Does Partial Discharge Testing Tell You?

Partial discharge, or PD, is a localized electrical discharge that does not completely bridge the insulation between conductors. It can indicate insulation defects that may deteriorate under electrical stress.

PD testing is used for both transformers and switchgear. It helps assess insulation under defined test conditions, but a passing result does not establish that every aspect of the equipment is satisfactory. It also does not guarantee a particular service life.

In conventional charge-based testing, the result is commonly expressed in picocoulombs (pC). This represents apparent charge, not the physical size of a defect. IEC 60270 provides the measurement framework, including calibration and interference considerations; equipment-specific requirements determine how the result is assessed.

Do Transformers and Switchgear Have the Same PD Requirements?

No. Sharing the same measurement unit does not mean sharing the same acceptance limit.

Equipment What Buyers Should Clarify
Dry-type transformers Confirm the applicable IEC 60076-11 requirements, prescribed test conditions and any stricter contractual guarantee. The standard’s 10 pC maximum applies under its specified test conditions—not to every type of electrical equipment.
Oil-immersed transformers Establish the required dielectric and PD test scope from the applicable transformer standard, equipment ratings and purchase specification. Do not copy the dry-type transformer limit.
Medium-voltage switchgear and RMUs Confirm whether PD testing is required for the supplied configuration, the applicable procedure and agreed acceptance criteria. Identify whether the report covers an individual component, an assembled functional unit or a defined group of units.

The distinction matters particularly for switchgear: a component test report does not, by itself, demonstrate the PD performance of the assembled panel. The scope of the evidence should match the acceptance requirement.

Five Checks Before Accepting a PD Test Report

1. Does the Report Identify the Supplied Equipment?

Check the serial number, model and relevant ratings against the order and nameplate.

For switchgear, also confirm which panel, functional unit or assembly was tested. A report for a similar design may support design verification, but it is not the same as a test record for the supplied equipment.

2. Is the Acceptance Basis Clear?

The report or referenced procedure should identify the applicable standard and edition, the test method and the acceptance criteria.

“PD: Pass” is a conclusion. Buyers still need to know the requirement against which that conclusion was reached.

3. Are the Test Conditions Traceable?

Look for the applied voltage, relevant voltage sequence, frequency, duration and measurement connections. These may appear in the report itself or in an identified test procedure.

A reading taken at one voltage cannot automatically be compared with a reading taken at another. Likewise, a factory acceptance measurement and an online condition-monitoring reading may use different methods and cannot simply be treated as equivalent.

4. Is the Measurement Reliable Enough to Support the Result?

PD testing measures small signals. Background interference and measurement sensitivity therefore matter.

Ask for sufficient information about calibration of the measuring system in the test circuit and the background noise level. An instrument’s calibration certificate alone does not describe the performance of the complete measurement arrangement. IEC 60270 addresses calibration and interference discrimination as part of charge-based PD measurement.

5. Are Results and Any Retests Documented?

The record should identify the relevant phases or measurement channels, the results and the acceptance conclusion.

If an unexpected reading led to investigation, corrective work or retesting, request the explanation and final disposition. An unexplained replacement result provides less useful evidence than a traceable record of what happened.

2026年7月31日 11_48_45.png

Is “Below 5 pC” Better Than “Below 10 pC”?

A lower guaranteed limit can be meaningful when the equipment, test conditions and measurement basis are comparable. However, a catalogue claim, a contractual guarantee and an actual measured result are different things.

Consider two documents:

  • Supplier A states “PD below 5 pC” in a brochure.
  • Supplier B provides a unit-specific report showing the result, test conditions and compliance with the agreed limit.

The brochure alone cannot establish that Supplier A’s delivered equipment performs better. The first step is to obtain comparable evidence.

Nor should a lower pC number be converted into a promise of longer service life. PD is one insulation assessment parameter, not a complete equipment quality score.

Agree on the Test Scope Before Production

Include PD requirements in the technical specification and inspection and test plan before production begins. Clarify:

  • Which equipment and assemblies require testing.
  • The applicable procedure and acceptance criteria.
  • Whether document review, remote witnessing or attendance is required.
  • Which reports and supporting records must be delivered.
  • How deviations and retesting will be handled.

Remote witnessing can improve visibility, but a video of an instrument screen does not replace a traceable report. For a broader transformer inspection framework, see our transformer factory acceptance testing guide.

Make Testing Requirements Part of Your Enquiry

When enquiring about DERUI ELECTRIC’s distribution transformers or medium-voltage switchgear, include the project’s inspection specification and any PD reporting or witness requirements.

Confirming these details early gives both parties a clear basis for discussing equipment scope, acceptance documentation and delivery arrangements.