Expo 2030 Riyadh Power Plan: 400 MW Grid Capacity
The Hidden Challenge Behind Expo 2030 Riyadh: Building a 400 MW Power System
A 6 million m² site, more than 42 million expected visits and a permanent electrical system that must be ready long before opening day.
Expo 2030 Riyadh will be one of the largest World Expo developments ever planned.
The site will cover approximately 6 million square metres, host more than 230 pavilions and is expected to receive more than 42 million visits.
But before the pavilions, transport systems and public spaces can operate, another project has to be completed behind the scenes:
A permanent power system with approximately 400 MW of connection capacity.
A 400 MW System Is More Than One Big Transformer
Expo 2030 Riyadh’s planned power infrastructure includes a dedicated 380/132 kV bulk supply point, three 132/13.8 kV primary substations and the associated transmission and distribution network.
Alfanar Projects has already announced a contract worth more than SAR 122 million to construct one of the 132/13.8 kV substations serving the Expo development.
The important point is that 400 MW at the grid connection is only useful if every downstream stage can safely transmit, transform, protect and distribute that power.

Expo 2030 Riyadh’s 400 MW connection depends on a complete chain of transmission, transformation and distribution infrastructure.
Why Must the Power System Be Ready in 2029?
Expo 2030 Riyadh will not open until October 2030, but the permanent electrical connection is targeted for completion by Q1 2029.
That timing is not excessive. It reflects how major electrical infrastructure is actually delivered.
Substations and distribution networks require engineering studies, equipment procurement, civil works, installation, testing and commissioning before the final facilities begin normal operation.
The electrical network must also support building commissioning, cooling systems, lighting, communications, safety systems, EV charging and operational trials before millions of visitors arrive.
Expo organizers have already awarded utility packages covering approximately 50 kilometres of infrastructure networks, including electrical and communications systems alongside other site utilities.
Power infrastructure is often not the final system to arrive. It is what allows many of the other systems to be commissioned.
400 MW Is Capacity—Not Energy Consumption
The 400 MW figure describes the planned permanent connection capacity. It does not mean the Expo will continuously consume 400 MW.
Publicly available project information reviewed for this article does not currently provide a verified forecast for total event electricity consumption in MWh or GWh, nor the individual MVA rating of each primary substation.
That distinction matters because electrical infrastructure is not designed around average consumption alone.
Peak demand, redundancy, simultaneous loads, cooling requirements, fault levels, maintenance conditions and future expansion all influence the final system capacity.
What Happens After 132 kV?
For electrical equipment manufacturers and EPC contractors, one of the most relevant parts of the project begins on the 13.8 kV side.
Once the primary substations step the voltage down, electricity still has to be distributed among more than 230 pavilions, commercial facilities, public infrastructure and supporting services.
This is where medium-Voltage Switchgear, distribution transformers, protection systems, feeders and low-voltage equipment become part of the power-delivery chain.
Equipment selection must therefore be coordinated. transformer capacity, switchgear ratings, short-circuit withstand capability, cable capacity and protection settings all need to match the same electrical system.

Once electricity reaches medium voltage, transformers, switchgear and protection equipment determine how reliably it reaches the final load.
What Does This Mean for a Smaller Industrial Project?
Most industrial customers will never need anything close to 400 MW.
But the planning logic scales down surprisingly well.
Consider a hypothetical manufacturing park with a 20 MW peak load.
The project still needs to determine how many transformers are required, how the load should be divided, whether critical production needs redundancy and how much spare capacity should be reserved for future expansion.
Engineers also need to calculate MV feeder requirements, switchgear ratings, short-circuit current, protection settings and cable capacity.
If the electrical system is designed only for today’s demand, adding another production line several years later may require expensive retrofits. Planning transformer bays, spare switchgear panels and cable routes in advance can make expansion significantly easier.
- Current and future peak load
- Incoming voltage level
- Transformer quantity and capacity
- MV and LV switchgear ratings
- Short-circuit withstand capability
- Protection coordination
- Redundancy requirements
- Future feeder and expansion space
The Infrastructure Visitors Will Never See
When Expo 2030 Riyadh opens, visitors will see pavilions, public spaces, architecture and new technologies.
Behind them will be an electrical system built years earlier around several substantial numbers:
Electrical capacity has to be planned before the load arrives.
From Large Developments to Industrial Distribution
Expo 2030 Riyadh operates at a much larger scale than the projects typically served by medium-voltage distribution equipment, but the underlying engineering principle is the same: transformer capacity, switchgear, protection and future expansion should be planned as one system.
Derui Electric manufactures transformers, MV and LV switchgear and related distribution equipment for overseas industrial and EPC projects, supporting equipment selection based on voltage level, capacity, operating conditions and future load requirements.
Frequently Asked Questions
How much electrical capacity is planned for Expo 2030 Riyadh?
The permanent grid connection is planned to provide approximately 400 MW of electrical capacity.
What substations are planned for Expo 2030 Riyadh?
Public project information describes a 380/132 kV bulk supply point and three 132/13.8 kV primary substations, together with associated transmission and distribution infrastructure.
Does 400 MW mean the Expo will continuously consume 400 MW?
No. The 400 MW figure refers to planned connection capacity. Actual electricity consumption will vary with operating conditions and demand.
Why is medium-voltage distribution important after the primary substation?
Medium-voltage switchgear, distribution transformers, protection and feeders are required to distribute power safely from the primary substations to buildings, facilities and final loads.
Planning a Medium-Voltage Distribution Project?
Share your incoming voltage, transformer capacity, load profile and future expansion requirements. Derui Electric can support transformer, MV/LV switchgear and distribution equipment selection for industrial and EPC projects.
Contact Derui ElectricSources
- Expo 2030 Riyadh: Official Expo 2030 Riyadh information
- Saudi Press Agency: Expo 2030 Riyadh permanent power connection
- Alfanar Projects: SAR 122+ million 132/13.8 kV substation contract
- Expo 2030 Riyadh: Utilities infrastructure contract











