Factory acceptance testing (FAT) gives transformer buyers an opportunity to verify agreed requirements before shipment. For procurement managers, EPC contractors and project owners, the key questions are practical: what will be tested, what evidence will be provided, and how will any non-conformities be resolved?
At DERUI ELECTRIC, buyers ask about remote witnessing, test documentation and inspection schedules when discussing their orders. Defining these requirements at the enquiry and contract stages helps both parties prepare for acceptance before the equipment is ready to ship.
This guide explains what a transformer FAT should cover, where PD testing during FAT fits into the inspection plan, and what buyers should confirm before releasing equipment for shipment.

1. What Is a Factory Acceptance Test (FAT)?
A factory acceptance test is an agreed programme of testing, inspection and document review carried out before equipment leaves the manufacturer's facility. For a transformer, it provides evidence that the supplied unit meets the applicable test requirements and purchase specification.
Depending on the contract, the buyer or an appointed inspector may witness selected tests in person or remotely. The acceptance package can include test reports, inspection records, witness sign-offs and any required conformity documents.
Testing requirements, witness points and shipment-release conditions should be agreed before production. Passing an individual test does not automatically close every contractual inspection or documentation requirement.
2. Why Are More Buyers Requesting FAT?
2.1 Reducing the Cost of Problems Found on Site
Correcting a problem after delivery may involve transport, site labour and changes to the commissioning schedule. FAT helps identify non-conformities while the equipment is still at the factory.
2.2 Verifying Compliance with Specifications
Buyers can review applicable routine test results, supporting design-verification reports and contractual requirements such as loss guarantees, voltage ratio and vector group. The agreed inspection plan defines which items are tested, witnessed or verified through documentation.
2.3 Managing Delivery and Commissioning Risks
A non-conforming transformer can disrupt the project schedule. Agreeing on acceptance criteria, document delivery and corrective-action procedures early makes it easier to resolve issues before shipment.
2.4 Gaining Visibility Before Shipment
In-person or remote witnessing allows buyers to observe agreed test activities and raise questions while the testing team is available. Witnessing complements the test records; it does not replace them.
2.5 Creating a Documented Acceptance Record
FAT creates a shared record of the equipment's tested condition before shipment. Together with packing, transport and site inspection records, this documentation can help clarify issues discovered later.
3. What Should a Transformer FAT Include?
The FAT scope should follow the applicable parts of IEC 60076, the transformer's ratings and the purchase specification. The inspection and test plan should distinguish tests performed on the supplied unit from design-verification reports and any additional tests agreed for the project.
Routine tests: Confirm the applicable measurements, such as winding resistance, voltage ratio and phase displacement, no-load loss and current, short-circuit impedance and load loss, and the required dielectric tests. For dry-type transformers within the scope of IEC 60076-11, partial discharge measurement forms part of routine testing.
Type and special tests: Identify which supporting reports are required and whether any additional testing must be performed for the order. Do not assume that every design-verification test will be repeated on every transformer.
Acceptance documents: Agree on the equipment identification, test procedures, measured results, acceptance criteria and any witness or retest records to be supplied.
PD Testing During FAT: What Buyers Should Verify
When partial discharge testing is included in a transformer FAT, buyers should confirm both the test requirements and the evidence needed for acceptance. A reading in picocoulombs (pC) should be assessed against the specified test conditions and agreed acceptance limit.
Before the test, clarify:
- Test scope: Which transformer and windings are covered, and which standard and procedure apply?
- Test conditions: What voltage sequence, measurement duration and measurement arrangement will be used?
- Acceptance evidence: Will the records identify the supplied unit, measured PD levels, acceptance limit, measuring-system calibration and background noise?
For oil-immersed transformers, establish the PD test requirements from the applicable dielectric test provisions and purchase specification. Do not automatically apply a dry-type transformer's acceptance limit.
If the buyer witnesses testing remotely, agree in advance how equipment identification and test records will be shown and delivered. A live instrument display should be supported by traceable documentation.
For equipment-specific requirements and detailed report checks, see our guide to PD testing during FAT for transformers and switchgear.
4. The Rise of Remote and Digital FAT
Remote FAT can allow buyers, engineers and inspectors to participate through live video and shared test records. It can reduce travel requirements and make it easier for project teams in different locations to attend.
Before the session, agree on the tests to be witnessed, camera coverage, access to results, recording arrangements and the process for raising questions. The buyer should be able to connect the equipment shown on screen with the serial numbers in the test documentation.
Whether remote witnessing is acceptable depends on the contract and inspection requirements. Where physical attendance is required, a video session should not be treated as an automatic substitute.
5. What the FAT Day Actually Looks Like
Before the test: Verify that the transformer nameplate matches the purchase order. Review the test schedule, procedures, relevant calibration records and acceptance criteria. Confirm the witness points and any documentation needed before testing starts.
During the test: Observe the agreed activities, check that serial numbers match the FAT documentation, review the available results and record questions or deviations. Complete witness records as required by the inspection plan.
After the test: Review the reports and outstanding items. Obtain the agreed supporting records, confirm corrective work or retesting where necessary, and complete acceptance and shipment-release documentation according to the contract.
6. What Buyers Should Look for in a Supplier's FAT Process
- Are the test procedures and acceptance criteria defined before testing?
- Can the test facility demonstrate the required capability, and does any required laboratory accreditation cover the relevant tests?
- Can the buyer witness the agreed tests in person or remotely?
- Will reports identify the supplied equipment and include measured values?
- Are customer-appointed third-party inspectors permitted under the agreed arrangements?
- Is there a documented process for deviations, corrective work and retesting?
7. FAT Checklist for Buyers
| Item | When to Confirm |
|---|---|
| Complete test scope and applicable standards | Before production |
| Witness requirements and inspection hold points | Before production |
| FAT dates and remote or in-person attendance | Before FAT |
| Relevant calibration records and test procedures | Before testing |
| Acceptance criteria for each applicable test | Before testing |
| PD test scope, conditions and reporting requirements, where applicable | Before testing |
| Nameplate and serial numbers match the order and test records | At FAT |
| Reports include measured values and acceptance conclusions | During final review |
| Deviations and required retests are documented and resolved | Before acceptance |
| Agreed accessories, spare parts and shipment documents | Before shipment release |
Use this checklist alongside the project inspection and test plan. The purchase specification determines which activities and documents are required for the order.
8. How DERUI ELECTRIC Approaches FAT
Buyers of DERUI ELECTRIC's distribution transformers can discuss test documentation, witnessing and third-party inspection requirements during the quotation and contract stages. Confirming the scope early helps align testing and shipment arrangements with the project schedule.
- Applicable routine tests, with type-test documentation and any additional testing agreed in the purchase specification.
- In-person or remote witnessing arrangements agreed for the order.
- Test reports identifying the equipment, measured results and applicable acceptance criteria.
- Coordination with customer-appointed third-party inspectors according to the agreed inspection plan.
- Test procedures, document requirements and acceptance arrangements defined before the scheduled FAT.
Include the project's inspection specification with your enquiry, particularly where PD reporting, additional testing or witness attendance is required.
9. Make FAT Part of the Procurement Plan
A well-defined transformer FAT connects the purchase specification with measurable acceptance evidence. Its value comes from an agreed test scope, traceable results and a clear process for resolving outstanding items before shipment.
For buyers, the practical step is to discuss testing and documentation when requesting a quotation. This gives both parties time to prepare the required records, schedule witnesses and confirm how acceptance will be completed.
Frequently Asked Questions
Can I skip FAT for a distribution transformer?
Distinguish the required factory tests from buyer-witnessed acceptance activities. Applicable testing requirements still apply even when the buyer does not attend. The purchase contract should define the inspection scope, documentation and witnessing requirements.
Who pays if FAT fails?
Responsibility for investigation, corrective work, retesting and repeat inspection should be defined in the contract. The cause of the non-conformity and any changes to the agreed specification need to be considered.
Should FAT be performed before final payment?
FAT acceptance, shipment release and payment milestones should be aligned in the purchase contract. Specify which reports and approvals are needed for each milestone rather than assuming that a standard payment arrangement applies to every order.
Can FAT replace third-party inspection?
FAT is a testing and acceptance activity; third-party inspection describes independent involvement in the agreed inspection scope. A third-party inspector may witness FAT and review its records. Whether additional inspections are needed depends on the project requirements.
What happens if a transformer fails FAT?
Document the non-conformity, investigate its cause and agree on corrective action. Any required retesting and final disposition should be recorded. Acceptance and shipment release should follow the contract and the agreed process for closing outstanding items.
Can FAT be conducted online?
Buyers can witness agreed FAT activities remotely while the physical tests are performed at the test facility. Confirm video coverage, equipment identification, access to results and document delivery beforehand. Remote witnessing must meet the project's acceptance requirements.
Is FAT witnessing required by IEC 60076?
IEC 60076 defines applicable transformer testing requirements. Purchaser witnessing and project-specific acceptance arrangements should be stated in the purchase specification and inspection and test plan.