What Transformers Are Used in EV Charging Infrastructure?
Electric vehicle adoption is accelerating at an unprecedented pace. Global EV sales surpassed 17 million units in 2025, and charging infrastructure deployment is struggling to keep up. Behind every fast charger, fleet depot, and highway charging hub lies a critical but often overlooked component: the transformer.
For charge point operators (CPOs), facility managers, and EPC contractors, transformer selection directly affects charging speed, grid connection costs, operational reliability, and long-term profitability. A poorly chosen transformer can cause voltage drops during peak demand, overloads from multiple fast chargers, harmonic distortion that trips protection devices, and excessive no‑load losses during idle overnight periods.
This guide explains the types of transformers used in EV charging infrastructure, key selection criteria, and how to avoid common mistakes that delay projects and increase costs.

1. Why EV Charging Transformers Are Different
Unlike traditional commercial or industrial loads, EV chargers create unique electrical demands:
- High and intermittent power draw – A single 150 kW DC fast charger can pull as much current as a small factory, but only when vehicles are connected.
- Significant harmonic distortion– AC/DC converters in fast chargers generate harmonics (5th, 7th, 11th, 13th orders) that can overheat standard transformers.
- Wide load variation – A charging station may sit at 10% load overnight and suddenly jump to 80–100% during peak hours.
- Outdoor installation – Most chargers are located in exposed environments: highways, parking lots, remote depots.
These characteristics demand purpose‑designed transformers, not generic distribution units.
2. Main Transformer Types Used in EV Charging
Pad‑Mounted transformers – Industry standard for public DC fast charging. Oil‑immersed, weatherproof, outdoor ground‑level. 500kVA–2.5MVA, 12kV–34.5kV to 208V–600V.
Substation Transformers – For large hubs (bus depots, truck plazas). 5–20 MVA, 35kV to 480V/600V, OLTC, forced cooling.
Dry‑Type transformers – Indoor/rooftop where fire codes prohibit oil. 100kVA–1.5MVA, up to 35kV, fire‑safe encapsulation, compact.
Pole‑Mounted transformers – Rural/low‑power Level 2 AC chargers. 25kVA–167kVA, single‑phase or small three‑phase, 7.2kV–34.5kV to 120/240V.
3. Key Technical Parameters for EV Charging Transformers
3.1 Rated Capacity (kVA) – Size with diversity factor (0.6–0.8) and 20% margin. Example: 8×150kW → 1250kVA recommended.
3.2 Harmonic Mitigation (K‑Factor) – K‑4 to K‑7 for Level 2 AC; K‑9 to K‑13 for DC fast chargers; K‑20 for ultra‑fast (≥350kW).
3.3 Voltage Regulation – Low impedance (3.5–5.5%) minimizes voltage drop; optional OLTC for volatile grids.
3.4 No‑Load Losses – Amorphous metal cores reduce idle losses by up to 70%, critical for stations with long overnight idle periods.
3.5 Environmental Protection – IP54/IP65, wide‑temp (-40°C to +55°C), C5‑M corrosion coating.

4. Common Pitfalls in EV Charging Transformer Procurement
- ❌ Undersizing – Leads to overheating, breaker tripping, limited charger output.
- ❌ Ignoring Harmonics – Standard transformers overheat and fail prematurely.
- ❌ Overlooking Idle Losses – High core loss wastes energy overnight; amorphous cores pay back quickly.
- ❌ Inadequate Future Capacity – Always include 20–30% spare capacity for additional chargers.
5. Why Derui Electric for EV Charging Transformers?
| Product Type | Capacity | Primary Voltage | Key Features |
|---|---|---|---|
| Pad‑Mounted Transformer | 500kVA – 3 MVA | 12kV – 34.5kV | K‑13 / K‑20, IP54, low noise, tamper‑resistant |
| Substation Transformer | 5 MVA – 20 MVA | 35kV – 69kV | OLTC, forced cooling, K‑20, C5‑M coating |
| Dry‑Type Transformer | 100kVA – 1.5 MVA | Up to 35kV | Fire‑safe, K‑factor ready, indoor/rooftop |
| Pole‑Mounted Transformer | 25kVA – 167kVA | 7.2kV – 34.5kV | Single/three‑phase, lightweight, outdoor durable |
Key advantages: Harmonic‑ready (K‑factor up to K‑20), amorphous core option (70% lower no‑load loss), low impedance (3.5–5.5%), optional OLTC, IEC 60076 certified, short lead times (12–16 weeks standard), global environmental adaptation (IP54/IP65, C5‑M, -40°C to +55°C).
Frequently Asked Questions (FAQ)
Q1: What size transformer do I need for a DC fast charging station?
A: Depends on number and power of chargers. A common formula: Transformer kVA = (Total charger kW × diversity factor 0.6–0.8) ÷ PF (0.95) + 20% margin. For 4×150kW chargers, ~900–1000 kVA is typical. Derui Electric provides free load analysis and sizing.
Q2: Do I need a K‑factor rated transformer for EV chargers?
A: Yes, for DC fast chargers (≥50kW). Standard transformers overheat from harmonics. Specify K‑9 to K‑13 for 50–150kW chargers; K‑20 for ≥350kW ultra‑fast chargers. For Level 2 AC chargers (≤22kW), K‑4 to K‑7 is sufficient.
Q3: Can I use a dry‑type transformer outdoors for EV charging?
A: Yes, but with limitations. Dry‑type transformers with IP54 or IP65 enclosures can be installed outdoors, but oil‑immersed pad‑mounted units are more common and cost‑effective for ground‑level fast charging sites. Dry‑type is preferred for indoor parking garages or rooftop installations due to fire safety.
6. Future Trends: Ultra‑Fast Charging and Solid‑State Transformers
As 350kW+ ultra‑fast chargers and megawatt charging for trucks become mainstream, transformer technology is evolving: higher K‑factor requirements (K‑30+), integrated transformer‑rectifier units, and solid‑state transformers (SST) with 98.5%+ efficiency. While SSTs are not yet cost‑competitive for most sites, early adopters should monitor this technology for 2028–2030 deployment.
7. Conclusion: Choose Wisely, Charge Reliably
Transformers are the silent enablers of the EV revolution. When planning your next charging site, prioritize correct sizing (including future expansion), K‑factor rating, low no‑load loss, environmental protection, and a reliable supplier with EV charging experience.
Need support for your EV charging infrastructure project?
Derui Electric provides purpose‑built transformers for EV fast charging, fleet depots, and public networks. Send us your site load data and charger specifications – we will provide sizing, loss calculations, and a technical quotation within 48 hours.
Contact Derui Electric →










