Leave Your Message
The Power Was There. The Grid Couldn’t Move It—And It Cost $6 Billion.
Product News

The Power Was There. The Grid Couldn’t Move It—And It Cost $6 Billion.

2026-08-22
U.S. POWER GRID

The Power Was There. The Grid Couldn’t Move It—And It Cost $6 Billion.

PJM’s congestion costs jumped 43% in the first half of 2026, showing how transmission bottlenecks can make available electricity much more expensive to deliver.

The electricity existed.

The customers wanted it.

But moving enough power from one part of the grid to another became increasingly expensive.

In the first half of 2026, PJM grid congestion costs reached $6 billion, according to its independent market monitor. That was 43% higher than a year earlier.

$6 Billion
PJM transmission congestion costs in H1 2026
+43%
Increase compared with the same period last year
8,920
Five-minute periods when 500 kV limits were hit or exceeded

8,920 Transmission Constraints

PJM serves around 67 million people across a large part of the eastern United States.

During the first six months of 2026, its 500 kV transmission system hit or exceeded operating limits during 8,920 five-minute periods.

A year earlier, that number was only 1,865.

Severe weather contributed to some of the congestion, while Northern Virginia—home to one of the world’s largest concentrations of data centers—was among the areas experiencing growing transmission pressure.

The problem was not simply whether electricity existed. It was whether the grid could move enough of it to where demand was growing.

More Generation Does Not Automatically Mean More Usable Power

Building another power plant does not solve every electricity problem.

Power still has to travel through transmission lines, substations, transformers, switchgear and distribution networks before it reaches the final load.

If one section of that chain cannot handle the required power flow, electricity may be available somewhere on the system while becoming difficult—or expensive—to deliver somewhere else.

PJM-power-delivery-bottleneck-infographic-1800x1000.png

Generating electricity is only part of the job. The grid must also be able to transmit, transform and distribute it.

The Same Principle Applies to a Factory

An industrial project is obviously much smaller than PJM.

But the engineering logic is similar.

A factory may have enough power available from the utility but still be unable to expand production if its transformer, Mv Switchgear, cables or downstream distribution system cannot support the additional load.

A larger transformer alone cannot solve an undersized switchgear or cable problem.

Likewise, new production equipment should not simply be connected without checking load growth, short-circuit levels, protection requirements and future expansion.

Before Expanding Industrial Load, Check the Whole System
  • Available utility capacity
  • transformer loading and future capacity
  • MV and Lv Switchgear ratings
  • Cable and busbar capacity
  • Short-circuit levels
  • Protection coordination

Why PJM Grid Congestion Cost $6 Billion

PJM’s real-time wholesale electricity cost increased from about $20.4 billion in the first half of 2025 to $29.4 billion in the same period of 2026.

Transmission-related price adjustments rose from around $2.1 billion to $6 billion.

PJM’s market monitor argues that some congestion costs have also been influenced by the way transmission limits are calculated, while PJM disputes parts of that analysis.

Whatever the market debate, the broader engineering issue remains: rapidly growing electricity demand is putting increasing pressure on the infrastructure between generation and the customer.

$6 Billion for a Bottleneck

$6 billion in six months.

Not because the electricity disappeared, but because delivering it through a constrained network became much more expensive.

Generating power is only half the job. The system must also be able to move, transform, protect and distribute it where it is needed.

From Grid Capacity to Industrial Distribution

Industrial power projects depend on more than available utility supply. Transformer capacity, MV and LV switchgear, protection, cable ratings and future load growth should be evaluated together.

Derui Electric manufactures transformers and complete transmission and distribution equipment for overseas industrial, EPC and distribution projects, supporting equipment selection based on voltage level, load requirements and actual operating conditions.

Frequently Asked Questions

What is PJM grid congestion?

Grid congestion occurs when transmission infrastructure cannot move all of the electricity that market participants want to send between different parts of the power system.

How much did PJM transmission congestion cost in 2026?

PJM transmission congestion costs reached approximately $6 billion in the first half of 2026, up about 43% from the same period a year earlier.

Can adding more generation solve grid congestion?

Not necessarily. New generation still depends on sufficient transmission, substation and downstream network capacity to deliver electricity to the areas where it is needed.

Why does this matter for industrial power projects?

Factory expansion depends on the capacity of the complete electrical chain, including available utility power, transformers, switchgear, cables, protection systems and downstream distribution.

Planning an Industrial Power Expansion?

Share your voltage level, transformer capacity, existing load and expansion requirements. Derui Electric can support transformer, MV/LV switchgear and distribution equipment selection for industrial and EPC projects.

Contact Derui Electric